Demolition scheduled for Monday Dec. 22 for Kravis Center
progression, per a Claremont McKenna College officials.
The work, during the Kravis Center construction, will include excavation of underground utility lines and removing concrete sidewalks that serve Roberts North.
The college community will have to deal with possible intermittent closures of Roberts South and North bathrooms when sewer and water lines are disconnected and reconnected.
There will be attempts to schedule the work during off-hours or with a 24 hour advance notice.
But air conditioning, heating and ventiliation will not be completed until mid-January for Roberts North. This will prevent comfort cooling or heating in the building until then.
Renowned architect Rafael Viñoly has designed the center.
Go to the news release here: http://www.cmc.edu/news/pressreleases/article.asp?article_id=1129