Recently in Construction Category
As part of the continuing I-215 widening project, Caltrans will close SR-259 between Highland Avenue and I-215 from 8 p.m. to 4 a.m. nightly through Thursday (February 9).
Caltrans' suggested detour is to exit at Highland Avenue, turn left to H Street and turn right. Travel south to Fifth Street, turn right and left on to southbound I-215.
Caltrans' suggested detour is to exit at Highland Avenue, turn left to H Street and turn right. Travel south to Fifth Street, turn right and left on to southbound I-215.
Sign work will prompt the closure of the connector from westbound SR-210 to northbound I-15 in Fontana.
The work will be done from 10 p.m. to 3 a.m. tonight and Tuesday night.
Caltrans will indicate a detour.
The work will be done from 10 p.m. to 3 a.m. tonight and Tuesday night.
Caltrans will indicate a detour.
Slab replacement will close lanes on the eastbound 10 Freeway nightly from 8 p.m. to 6 a.m. tonight (January 30) through Thursday (February 2).
Lanes #3 and #4 from Wabash Avenue to Yucaipa Boulevard will be closed during construction. Expect delays.
Lanes #3 and #4 from Wabash Avenue to Yucaipa Boulevard will be closed during construction. Expect delays.
Caltrans will be doing emergency roadwork on the 10 Freeway to repair the median in Montclair that was damaged during last week's big rig accident.
The repair schedule is as follows:
The repair schedule is as follows:
- 10 p.m. Friday (January 27) to 11 a.m. Saturday (January 28): Eastbound carpool lane closed
- 11 p.m. Friday to 7 a.m. Saturday: Eastbound carpool and #1 lane closed
- 10 p.m. to midnight Friday: Westbound carpool lane closed
- Midnight to 8 a.m. Saturday: Westbound carpool lane and #1 lane closed
- 8 to 11 a.m. Saturday: Westbound carpool lane closed
- 11 p.m. to midnight Saturday: Eastbound carpool lane closed
- Midnight to 9 a.m. Sunday (January 29): Eastbound carpool and #1 lane closed
- 9 to 11 a.m. Sunday: Eastbound carpool lane closed
- 11 p.m. Saturday to 11 a.m. Sunday: Westbound carpool and #1 lane closed
Shoulder work will close the #1 lane (which means only one lane will remaine open) on the southbound I-215 from Palm Avenue to University Parkway this week.
The work will be done from 9 a.m. to 2 p.m. Tuesday (January 10) through Thursday (January 12).
The work will be done from 9 a.m. to 2 p.m. Tuesday (January 10) through Thursday (January 12).
Just got a copy of a memo from Caltrans:
Caltrans and MCM Construction will be opening the northbound I-215 to the westbound SR-210 connector on Thursday morning, 12/22/11. This opening comes 15 months ahead of schedule. MCM Construction and Caltrans have worked diligently to get this connector open as they recognize the importance to motorists.
This connector will reduce travel time as motorists will not have to exit the freeway in order to make this transition. It will also reduce traffic on local city streets.
The eastbound SR-210 to southbound I-215 connector is scheduled to open in March of 2012 at least nine months ahead of schedule.
The southbound SR-259 will close from 8 p.m. to 4 a.m. through Thursday (December 22). For a detour, Caltrans is suggesting to exit the southbound SR-259 at Highland Avenue, turn left, then right on H Street and re-enter southbound I-215 at Orange Street (just below Base Line).
Also on those dates, various lanes on north- and southbound on I-215 between Rialto Avenue and University Parkway will close (southbound from 8 p.m. to 4 a.m., northbound between 10 p.m. and 6 a.m.). No detours are planned, as at least one lane is expected to be open.
A milestone should be reached this week as the northbound I-215 to the westbound SR-210 connector is scheduled to open mid-week.
For up-to-date information, follow @215News on Twitter.
Also on those dates, various lanes on north- and southbound on I-215 between Rialto Avenue and University Parkway will close (southbound from 8 p.m. to 4 a.m., northbound between 10 p.m. and 6 a.m.). No detours are planned, as at least one lane is expected to be open.
A milestone should be reached this week as the northbound I-215 to the westbound SR-210 connector is scheduled to open mid-week.
For up-to-date information, follow @215News on Twitter.
The westbound I-10 connector to southbound I-215 will close from 6 a.m. to noon Saturday (December 10) for maintenance work.
Possible alternatives include:
Possible alternatives include:
- Continuing westbound to Valley Boulevard, heading west on Valley to Mount Vernon Avenue, crossing over the freeway and re-entering eastbound I-10 to the southbound I-215
- Heading north on I-215, exiting at Orange Show Road, crossing over the freeway and entering the southbound I-215
Slab replacement work at the I-15/SR-60 interchange in Ontario will cause nighttime closures for part of next week.
Here's what we're looking at:
Closures
Delays are expected, so Caltrans is suggesting alternate routes if possible.
Here's what we're looking at:
Closures
- The southbound I-15 connector to westbound SR-60
- Westbound SR-60 lanes 2, 3 and 4 between Milliken Avenue and Archibald Avenue
- Westbound SR-60 Milliken Avenue on-ramp, Haven Avenue on- and off-ramps, and Archibald Avenue off-ramp
Delays are expected, so Caltrans is suggesting alternate routes if possible.
The connector road from eastbound (really, southbound at that point) SR-210 to westbound I-10 will be closed from 6 a.m. to noon Saturday (October 8) for guardrail repair.
You've got several options for a detour. Here are a couple:
You've got several options for a detour. Here are a couple:
- Exit at San Bernardino Avenue, turn left to Alabama Street, then left to the onramp for eastbound I-10.
- Take the connector to eastbound I-10, exit at Orange Street, go forward at the end of the offramp, turn left at Orange Street to the westbound I-10 onramp.
The number 3 and 4 lanes of eastbound I-10 just before Cherry Avenue will be closed from 9 a.m. to 3 p.m. today (September 8) so Caltrans crews can perform emergency slab replacement. Two lanes will remain open for traffic.
The eastbound Etiwanda Avenue on-ramp and Cherry Avenue off-ramp will also be closed during that time.
The eastbound Etiwanda Avenue on-ramp and Cherry Avenue off-ramp will also be closed during that time.
The southbound SR-259 will close from 8 p.m. to 4 a.m.nightly Sunday (August 7) through Thursday (August 11) as part of the ongoing I-215 widening project.
Caltrans is suggesting the following detour: Exit Highland Avenue from SR-259, turn left, turn right on H Street and travel south, entering southbound I-215 from the Orange Street onramp.
Also, the northbound Highland Avenue offramp from SR-259 is closed through 5 a.m. Monday (August 8). Caltrans is suggesting continuing to the E Street offramp and turning right to Highland Avenue.
Plus, the Second Street onramp to southbound I-215 is closed through 3 p.m. Monday (August 8). Caltrans is suggesting traveling south on either G or I streets to Mill Street to enter southbound I-215.
In addition, Third Street will close between G and I streets from 9 p.m. to 5 a.m. Sunday (August 7) and Second Street will close between G and I streets from 10 p.m. to 6 a.m. Thursday (August 11). In both cases, Caltrans is suggesting traveling south on either G or I streets to Rialto Avenue to cross under I-215.
For the latest updates, follow 215News on Twitter.
Caltrans is suggesting the following detour: Exit Highland Avenue from SR-259, turn left, turn right on H Street and travel south, entering southbound I-215 from the Orange Street onramp.
Also, the northbound Highland Avenue offramp from SR-259 is closed through 5 a.m. Monday (August 8). Caltrans is suggesting continuing to the E Street offramp and turning right to Highland Avenue.
Plus, the Second Street onramp to southbound I-215 is closed through 3 p.m. Monday (August 8). Caltrans is suggesting traveling south on either G or I streets to Mill Street to enter southbound I-215.
In addition, Third Street will close between G and I streets from 9 p.m. to 5 a.m. Sunday (August 7) and Second Street will close between G and I streets from 10 p.m. to 6 a.m. Thursday (August 11). In both cases, Caltrans is suggesting traveling south on either G or I streets to Rialto Avenue to cross under I-215.
For the latest updates, follow 215News on Twitter.
The area around the Guthrie Interchange will see some maintenance construction activity this weekend, but the time frames are short, so it shouldn't cause too much of a problem.
From 6 a.m. to 2 p.m. Saturday (July 31), the southbound I-215 connectors to east- and westbound I-10 will be closed to replace stolen electrical wiring and miscellaneous maintenance repairs.
From 6 a.m. to 11 a.m. Sunday (July 31), the westbound I-10 connectors to north- and southbound I-215 will be closed for miscellaneous maintenance repairs.
Also, from 10 a.m. to 1 p.m. Sunday, the Inland Center Drive offramp of northbound I-215 will close for guardrail repair.
From 6 a.m. to 2 p.m. Saturday (July 31), the southbound I-215 connectors to east- and westbound I-10 will be closed to replace stolen electrical wiring and miscellaneous maintenance repairs.
From 6 a.m. to 11 a.m. Sunday (July 31), the westbound I-10 connectors to north- and southbound I-215 will be closed for miscellaneous maintenance repairs.
Also, from 10 a.m. to 1 p.m. Sunday, the Inland Center Drive offramp of northbound I-215 will close for guardrail repair.
The connector from eastbound (although at that point, it's really southbound) SR-210 to westbound I-10 will be closed from 6 a.m. to noon Sunday (July 24) to repair the guardrail.
Possible detours:
Possible detours:
- Exit at San Bernardino Aveune, turn right to Alabama Street and left on Alabama Street past Lugonia Avenue to connect to westbound I-10.
- Connect to eastbound I-10, exit Orange Street, go forward to Orange Street, turn left on Orange Street and enter westbound I-10.
Planning a trip to Vegas or Laughlin this summer? You might want to pay attention.
Two pavement resurfacing projects are starting Monday (July 18) that might slow your drive.
One is on I-15 between Rasor Road to the Nevada state line. The other is on I-40 from Crucero Road to Kelbaker Road.
Work on both projects will take place from 9 p.m. to 6 a.m. Monday through Friday. One lane will remain open at all times.
Both projects are scheduled to be completed by October.
Two pavement resurfacing projects are starting Monday (July 18) that might slow your drive.
One is on I-15 between Rasor Road to the Nevada state line. The other is on I-40 from Crucero Road to Kelbaker Road.
Work on both projects will take place from 9 p.m. to 6 a.m. Monday through Friday. One lane will remain open at all times.
Both projects are scheduled to be completed by October.
Next week's 215 widening project-related construction will be more tolerable than this week's.
The only full closure will be the southbound SR-259, which will close from 8 p.m. to 4 a.m. nightly, Sunday (July 17) through Thursday (July 21).
Caltrans' suggested detour: Head south on SR-259 from westbound SR-210, exit Highland Avenue, turn left to H Street, right on H Street to Orange Street and turn right and enter southbound I-215.
Also, the Massachusetts Avenue bridge remains closed while the switch is made from the old bridge to the new bridge. It is scheduled to reopen July 25.
Various lane closures will take place from 8 p.m. to 6 a.m. nightly, Sunday (July 17) to Thursday (July 21) on both north- and southbound I-215 between Rialto Avenue and University Parkway, but at least one lane will remain open, so no detours are necessary.
Follow the jump for a map.
The only full closure will be the southbound SR-259, which will close from 8 p.m. to 4 a.m. nightly, Sunday (July 17) through Thursday (July 21).
Caltrans' suggested detour: Head south on SR-259 from westbound SR-210, exit Highland Avenue, turn left to H Street, right on H Street to Orange Street and turn right and enter southbound I-215.
Also, the Massachusetts Avenue bridge remains closed while the switch is made from the old bridge to the new bridge. It is scheduled to reopen July 25.
Various lane closures will take place from 8 p.m. to 6 a.m. nightly, Sunday (July 17) to Thursday (July 21) on both north- and southbound I-215 between Rialto Avenue and University Parkway, but at least one lane will remain open, so no detours are necessary.
Follow the jump for a map.
Continue reading Southbound SR-259 to close several nights next week.
Next week is going to be rough one for anyone trying to drive through San Bernardino at night.
There are a slew of closures scheduled in connection with the I-215 widening project.
Here's a list:
For the complete list (with Caltrans' suggested detours) click here. You might want to print a copy and keep it in your car if you're thinking of heading through San Bernardino at night.
For more information and updates on the 215 widening project, follow 215News on Twitter.
There are a slew of closures scheduled in connection with the I-215 widening project.
Here's a list:
- Sunday (July 10) to Wednesday (July 13), 8 p.m. to 6 a.m. nightly: Full northbound I-215 closure from 10th Street to Massachusetts Avenue
- Thursday (July 14), 8 p.m. to 6 a.m.: Full northbound I-215 closure from 10th Street to SR-210 connector
- Sunday (July 10) to Thursday (July 14), 8 p.m. to 6 a.m. nightly: Full southbound I-215 closure from SR-210 connector to Orange Street
- Monday (July 11) and Tuesday (July 12), 10 p.m. to 6 a.m. nightly: Full closure connector from southbound I-215 to eastbound SR-210
- Monday (July 11) and Tuesday (July 12), 10 p.m. to 6 a.m. nightly: Full closure connector from eastbound SR-210 to northbound I-215
- Wednesday (July 13) and Thursday (July 14), 10 p.m. to 6 a.m.: Full westbound SR-210 closure from northbound I-215 connector to southbound I-215 connector
- Sunday (July 10) to Thursday (July 14), 8 p.m. to 6 a.m. nightly: Full northbound SR-259 connector closure
- Wednesday (July 13) and Thursday (July 14), 10 p.m. to 6 a.m. nightly: Full Third Street closure at I-215
- Sunday (July 10) to Thursday (July 14), 8 p.m. to 6 a.m. nightly: Various lane closures on north- and southbound I-215 between Rialto Avenue and University Parkway
For the complete list (with Caltrans' suggested detours) click here. You might want to print a copy and keep it in your car if you're thinking of heading through San Bernardino at night.
For more information and updates on the 215 widening project, follow 215News on Twitter.
A paving project begun this week to repair damaged pavement on SR-18 in the San Bernardino Mountains will continue through late August.
Work is being done on the back side of the San Bernardino Mountains from Pine View Drive (post mile 53) to Meridian Road (post mile 72.1) between Big Bear and Apple Valley.
Work hours are Monday through Friday from 9 a.m. to 6 p.m.
Flagging will take place during the work -- delays are expected to be approximately 15 to 20 minutes.
Work is being done on the back side of the San Bernardino Mountains from Pine View Drive (post mile 53) to Meridian Road (post mile 72.1) between Big Bear and Apple Valley.
Work hours are Monday through Friday from 9 a.m. to 6 p.m.
Flagging will take place during the work -- delays are expected to be approximately 15 to 20 minutes.
A paving project on northbound I-15 in Fontana will shut down two lanes and an offramp from 8 a.m. to 2 p.m. today (June 22) and Thursday (June 23).
The number 3 and 4 lanes from Duncan Canyon Road to Sierra Avenue and the Sierra Avenue offramp will be affected by the construction.
The number 3 and 4 lanes from Duncan Canyon Road to Sierra Avenue and the Sierra Avenue offramp will be affected by the construction.
The commute through Riverside is going to be rough going from 9 a.m. to 1 p.m. today (June 15) due to several closures on both the north- and southbound I-215. The closures are due to bridge inspections.
Caltrans is urging commuters to avoid the area if possible.
Here's the breakdown of what's going to be closed when:
Caltrans is urging commuters to avoid the area if possible.
Here's the breakdown of what's going to be closed when:
- Northbound I-215/westbound SR-60 at Iowa Avenue: Number 4 and 5 lanes, along with the University Avenue and Blaine Street offramps closed 9 to 11 a.m.
- Southbound I-215 at Columbia Avenue: Number 3 and auxiliary lanes, along with the Columbia Avenue on- and offramps closed 10:30 a.m. to noon; number 1 and 2 lanes closed from 11 a.m. to 1 p.m.
The ongoing I-215 widening project is going to cause problems for those driving through San Bernardino tonight.
Both north- and southbound I-215 will be closed from 9 p.m. tonight (June 9) through 5 a.m. tomorrow (June 10).
The southbound closure will be from SR-210 to SR-259. The northbound closure will be between Muscupiabe Drive to SR-210.
Your best bet is to avoid the area, but if you have to drive through town, Caltrans is offering the following detours:
Follow the jump for a map of the detours.
Both north- and southbound I-215 will be closed from 9 p.m. tonight (June 9) through 5 a.m. tomorrow (June 10).
The southbound closure will be from SR-210 to SR-259. The northbound closure will be between Muscupiabe Drive to SR-210.
Your best bet is to avoid the area, but if you have to drive through town, Caltrans is offering the following detours:
- Northbound: Exit Muscupiabe Drive, turn right on Highland Avenue, enter the northbound SR-259, exit E Street and turn left, turn left on 30th Street, turn left again on H Street, head west on SR-210 and take the northbound I-215 connector.
- Southbound: Take the eastbound SR-210 connector, exit H Street and turn left, turn right on 30th Street, and enter the southbound SR-259.
Follow the jump for a map of the detours.
Continue reading Complete I-215 closure tonight.
SR-330, which was washed out in several spots during this winter's storms, but has recently been open to commuter traffic twice a day, will again close Wednesday (May 18) through Friday (May 20).
The full closures are necessary to prepare for the planned unrestricted access during Memorial Day weekend.
Caltrans is expecting to re-open the route to commuter traffic on Monday, May 23, however, further full closures may be necessary before Memorial Day.
For updates, visit the Caltrans District 8 website or their Twitter and Facebook pages. You may also call Caltrans during business hours at 909-383-4631.
The full closures are necessary to prepare for the planned unrestricted access during Memorial Day weekend.
Caltrans is expecting to re-open the route to commuter traffic on Monday, May 23, however, further full closures may be necessary before Memorial Day.
For updates, visit the Caltrans District 8 website or their Twitter and Facebook pages. You may also call Caltrans during business hours at 909-383-4631.
Again, the northbound SR-259 connector from the northbound-215 to the eastbound SR-210 will be closed overnight for most of this week.
Here are the closure times:
Also, various lanes will be closed between Rialto Avenue and University Parkway on the north- and southbound I-215 from 8 p.m. to 6 a.m. tonight (May 8) through Thursday (May 12), but no detour is necessary, since at least one lane is expected to remain open.
A look ahead: Next week, Caltrans is planning full I-215 closures between Muscupiabe Drive to the SR-210 connector. Northbound closures are scheduled between 9 p.m. and 5 a.m. May 16 and 17. Southbound closures are scheduled between 9 p.m. and 5 a.m. May 18 through 20.
For the latest updates, follow 215News on Twitter.
Here are the closure times:
- 10 p.m. to 6 a.m. tonight (May 8) through Thursday (May 12).
Also, various lanes will be closed between Rialto Avenue and University Parkway on the north- and southbound I-215 from 8 p.m. to 6 a.m. tonight (May 8) through Thursday (May 12), but no detour is necessary, since at least one lane is expected to remain open.
A look ahead: Next week, Caltrans is planning full I-215 closures between Muscupiabe Drive to the SR-210 connector. Northbound closures are scheduled between 9 p.m. and 5 a.m. May 16 and 17. Southbound closures are scheduled between 9 p.m. and 5 a.m. May 18 through 20.
For the latest updates, follow 215News on Twitter.
The northbound SR-259 connector from the northbound-215 to the eastbound SR-210 will be closed overnight for most of next week.
Here are the closure times:
Also, various lanes will be closed between Rialto Avenue and University Parkway on the north- and southbound I-215 midnight to 6 a.m. Monday, April 25, and 8 p.m. to 6 a.m. Monday, April 25, to Thursday, April 28, but no detour is necessary, since at least one lane is expected to remain open.
For the latest updates, follow 215News on Twitter.
Here are the closure times:
- Midnight to 6 a.m. Monday, April 25.
- 10 p.m. to 6 a.m. Monday, April 25, to Thursday, April 28.
Also, various lanes will be closed between Rialto Avenue and University Parkway on the north- and southbound I-215 midnight to 6 a.m. Monday, April 25, and 8 p.m. to 6 a.m. Monday, April 25, to Thursday, April 28, but no detour is necessary, since at least one lane is expected to remain open.
For the latest updates, follow 215News on Twitter.
Caltrans is continuing work on two emergency repair projects to replace deteriorating pavement in the Cajon Pass and in Chino/Ontario.
The work will be done at night and at least two lanes will be open, so the impact to commuters should be minimal.
Here's the most recent schedule:
The work will be done at night and at least two lanes will be open, so the impact to commuters should be minimal.
Here's the most recent schedule:
- Cajon Pass: 9 p.m. to midnight, April 20, I-15 southbound from the brake check area to SR-138.
- Chino/Ontario: 9 p.m. to 4 a.m, April 18-22 and 25-29, SR-60 westbound between Haven Avenue and Central Avenue.
Caltrans is initiating two emergency repair projects to replace deteriorating pavement in the Cajon Pass and in Chino/Ontario.
The work will be done at night and at least two lanes will be open, so the impact to commuters should be minimal.
Here's the schedule:
The work will be done at night and at least two lanes will be open, so the impact to commuters should be minimal.
Here's the schedule:
- Cajon Pass: 9 p.m. to 5 a.m, April 11 to 15, I-15 southbound from the brake check area to SR-138.
- Chino/Ontario: 9 p.m. to 4 a.m, April 11 to 15, SR-60 westbound between Haven Avenue and Central Avenue.
More closures to report during the ongoing I-215 widening project beginning Sunday (March 27).
Here's what we're looking at:
10 p.m. to 6 a.m. Sunday (March 27) to Tuesday (March 29): Northbound SR-259 closed. Detour: Exit at 10th Street from northbound I-215, turn left on H Street and left again on Highland Avenue to northbound SR-259.
8 p.m. to 6 a.m. Sunday (March 27) to Tuesday (March 29): Various lane closures northbound and southbound between Rialto Avenue and University Parkway. No detour is necessary, since at least one lane will remain open.
9 a.m. to 3 p.m. Monday (March 28) and Tuesday (March 29): Southbound I-215 to eastbound SR-210 connector closed. Detour: Take the westbound SR-210 connector, exit State Street and turn left to access ramp for eastbound SR-210.
9 a.m. to 3 p.m. Monday (March 28) and Tuesday (March 29): Eastbound SR-210 to northbound I-215 connector closed. Detour: Take the westbound SR-210 connector, exit State Street and turn left to access ramp for eastbound SR-210. Detour: Take eastbound SR-210 past I-215, exit H Street and turn left to access the westbound SR-210 ramp to connect to northbound I-215.
For more information and updates on the 215 widening project, follow 215News on Twitter.
Follow the jump for the map.
Here's what we're looking at:
10 p.m. to 6 a.m. Sunday (March 27) to Tuesday (March 29): Northbound SR-259 closed. Detour: Exit at 10th Street from northbound I-215, turn left on H Street and left again on Highland Avenue to northbound SR-259.
8 p.m. to 6 a.m. Sunday (March 27) to Tuesday (March 29): Various lane closures northbound and southbound between Rialto Avenue and University Parkway. No detour is necessary, since at least one lane will remain open.
9 a.m. to 3 p.m. Monday (March 28) and Tuesday (March 29): Southbound I-215 to eastbound SR-210 connector closed. Detour: Take the westbound SR-210 connector, exit State Street and turn left to access ramp for eastbound SR-210.
9 a.m. to 3 p.m. Monday (March 28) and Tuesday (March 29): Eastbound SR-210 to northbound I-215 connector closed. Detour: Take the westbound SR-210 connector, exit State Street and turn left to access ramp for eastbound SR-210. Detour: Take eastbound SR-210 past I-215, exit H Street and turn left to access the westbound SR-210 ramp to connect to northbound I-215.
For more information and updates on the 215 widening project, follow 215News on Twitter.
Follow the jump for the map.
Continue reading I-215 construction, March 27 to 29.
Construction continues this week I-15 in the Cajon Pass on the emergency paving
project to repair pavement damaged during the recent storms.
The next two days of scheduled closures are from 8 a.m. to 3 p.m. Tuesday (February 22) and Wednesday (February 23).
Work will be done on southbound lanes, south of the truck scales, both days, dependent on cooperative weather.
Detours are not necessary, since at least two lanes will be open during the closures.
The next two days of scheduled closures are from 8 a.m. to 3 p.m. Tuesday (February 22) and Wednesday (February 23).
Work will be done on southbound lanes, south of the truck scales, both days, dependent on cooperative weather.
Detours are not necessary, since at least two lanes will be open during the closures.
Construction continues on I-15 in the Cajon Pass on the emergency paving project to repair pavement damaged during the recent storms.
The next two days of scheduled closures are from 8 a.m. to 3 p.m. Tuesday (February 15) and Wednesday (February 16).
Work will be done on southbound lanes, south of the truck scales, both days.
Detours are not necessary, as at least two lanes will be open during the closures, but Caltrans is warning motorists to expect "lengthy delays."
The next two days of scheduled closures are from 8 a.m. to 3 p.m. Tuesday (February 15) and Wednesday (February 16).
Work will be done on southbound lanes, south of the truck scales, both days.
Detours are not necessary, as at least two lanes will be open during the closures, but Caltrans is warning motorists to expect "lengthy delays."
Northbound I-215 in San Bernardino will be closed between Muscupiabe Drive and the 210 Freeway from 9 p.m. tonight (February 10) to 5 a.m. tomorrow (February 11). In addition, the connector to SR-259 will be closed during that same time.
Also, alternating lanes, both north- and southbound, between Rialto Avenue and University Parkway will be closed. Detours will not be necessary, since at least one lane will be open.
Follow the jump for a map.
Also, alternating lanes, both north- and southbound, between Rialto Avenue and University Parkway will be closed. Detours will not be necessary, since at least one lane will be open.
Follow the jump for a map.
Continue reading Another northbound I-215 full closure tonight.
Caltrans today began an emergency paving project to repair pavement damaged during the recent storms.
The work will be done from 8:30 a.m. to 3 p.m. Tuesday through Thursday on southbound lanes between Oak Hill Road and Cleghorn Road.
At least one lane will be open at all times, but Caltrans is warning to expect delays of up to four hours.
Once the southbound lanes are repaired (Caltrans is estimating a week or so), work will switch to the northbound side.
The entire project is expected to be complete January 28.
Update: Work on the northbound side will continue from 8:30 a.m. to 3 p.m. Tuesday (January 25) through Thursday (January 27), just south of the truck scales that are just south of SR138.
At least two lanes will be open at all time.
Caltrans is suggesting the following detour/non-detour: "LA County motorists going to the High Desert area or toward Barstow, Baker and Vegas may use I-5 north to SR-14 toward Palmdale, then take SR-138 east to SR-18 back to I-15. Inland Empire or Orange County motorists traveling I-15 northbound this week are advised to avoid travel during work hours."
The work will be done from 8:30 a.m. to 3 p.m. Tuesday through Thursday on southbound lanes between Oak Hill Road and Cleghorn Road.
At least one lane will be open at all times, but Caltrans is warning to expect delays of up to four hours.
Once the southbound lanes are repaired (Caltrans is estimating a week or so), work will switch to the northbound side.
The entire project is expected to be complete January 28.
Update: Work on the northbound side will continue from 8:30 a.m. to 3 p.m. Tuesday (January 25) through Thursday (January 27), just south of the truck scales that are just south of SR138.
At least two lanes will be open at all time.
Caltrans is suggesting the following detour/non-detour: "LA County motorists going to the High Desert area or toward Barstow, Baker and Vegas may use I-5 north to SR-14 toward Palmdale, then take SR-138 east to SR-18 back to I-15. Inland Empire or Orange County motorists traveling I-15 northbound this week are advised to avoid travel during work hours."
Crews will be closing I-215 in both directions from 9 p.m. tonight to 5 a.m. Tuesday and again from 9 p.m. Tuesday to 5 a.m. Wednesday for removal of the temporary structures at the Ninth Street bridge.
Caltrans is suggesting the following detours during the closure:
Northbound -- Exit Second Street, turn right to G Street. Turn left on G Street (which becomes H Street). Continue on H Street and make a left on 10th Street to the northbound I-215.
Southbound -- Exit Mount Vernon and continue south to Fifth Street. Turn left on Fifth Street to H Street. Make a right on H Street (which becomes G Street) and another right on Second Street to the southbound I-215 on-ramp.
For more information on the 215 widening project, follow 215News on Twitter.
Follow the jump for a map of the construction zone.
Caltrans is suggesting the following detours during the closure:
Northbound -- Exit Second Street, turn right to G Street. Turn left on G Street (which becomes H Street). Continue on H Street and make a left on 10th Street to the northbound I-215.
Southbound -- Exit Mount Vernon and continue south to Fifth Street. Turn left on Fifth Street to H Street. Make a right on H Street (which becomes G Street) and another right on Second Street to the southbound I-215 on-ramp.
For more information on the 215 widening project, follow 215News on Twitter.
Follow the jump for a map of the construction zone.
Continue reading North- and southbound I-215 closed tonight and Tuesday night.
The connector from northbound I-15 to eastbound I-10 in Ontario will be closed from 10 p.m. Friday (December 10) through 5 a.m. Monday (December 13).
The closure is due to concrete work.
Caltrans' suggested detour is to exit at Jurupa Street and head east to Etiwanda Avenue. Then head north on Etiwanda Avenue to I-10.
Follow the jump for a map.
The closure is due to concrete work.
Caltrans' suggested detour is to exit at Jurupa Street and head east to Etiwanda Avenue. Then head north on Etiwanda Avenue to I-10.
Follow the jump for a map.
Continue reading I-15 connector to I-10 closed this weekend.
There are several closures associated with the I-215 widening project this upcoming week.
- 10 p.m., Monday, December 6, to 5 a.m. Tuesday, December 7: Eastbound SR-210 to northbound I-215 connector closed.
Detour: Continue eastbound on SR-210, exit H Street, turn left onto H Street and left again onto westbound SR-210 to northbound I-215.
- 10 p.m. to 5 a.m. nightly, Monday, December 6 though Thursday, December 9: SR-210 to I-215 connector lane closures.
Detour: No detour planned as one lane is expected to be open at all times.
- 8 p.m. to 6 a.m. nightly, Monday, December 6 though Thursday, December 9: Varying north- and southbound I-215 lane closures between Rialto Avenue and University Parkway.
Detour: No detour planned as one lane is expected to be open at all times.
- 9 p.m. Friday, December 10 to 5 a.m. Monday, December 12: Full intersection closure at Base Line and H Street.
Detour: Base Line traffic, use 16th Street to the north or Fifth Street to the south. H Street traffic, use G Street. All local businesses will be accessible during the closure.
- 8 p.m. Saturday, December 11 to 8 p.m. Sunday, December 12: Southbound I-215 closed at Mount Vernon Avenue.
Detour: Exit 27th Street/Mount Vernon Avenue, continue south on Mount Vernon Avenue to Fifth Street. Turn left on Fifth Street, right on H Street, right on Second Street and left onto southbound I-215.Follow the jump to see a map of the closures.
Click here for a PDF regarding the closure.
Continue reading I-215 construction, December 6 to 11.
There's a couple of maintenance construction projects that may cause havoc with your drive through Ontario and Fontana the next couple of weeks.
First up is a guardrail repair scheduled from 8:00 a.m. to 2:00 p.m. Thursday (December 9) in Ontario. The northbound Jurupa Street onramp and the number 6 lane from Jurupa Street to the I-10 connector are scheduled to be closed.
Then, from 7 p.m. December 13 to 4 a.m. December 14, the southbound number 2, 3 and 4 lanes will be closed from Sierra Avenue to Summit Avenue in Fontana, for a slab replacement project.
Follow the jump for maps of the closures.
First up is a guardrail repair scheduled from 8:00 a.m. to 2:00 p.m. Thursday (December 9) in Ontario. The northbound Jurupa Street onramp and the number 6 lane from Jurupa Street to the I-10 connector are scheduled to be closed.
Then, from 7 p.m. December 13 to 4 a.m. December 14, the southbound number 2, 3 and 4 lanes will be closed from Sierra Avenue to Summit Avenue in Fontana, for a slab replacement project.
Follow the jump for maps of the closures.
Continue reading Maintenance roadwork scheduled for I-15.
Caltrans is placing a moratorium on lane closures over the Thanksgiving holiday.
There are no planned lane closures from 6 a.m. Wednesday (November 24) through 6 p.m. Monday (November 29).
However, be aware that closures may take place on state highways in the event of emergency work, weather related issues or other unforeseen events.
Caltrans is also offering these holiday driving safety tips:
There are no planned lane closures from 6 a.m. Wednesday (November 24) through 6 p.m. Monday (November 29).
However, be aware that closures may take place on state highways in the event of emergency work, weather related issues or other unforeseen events.
Caltrans is also offering these holiday driving safety tips:
- Never drink and drive and always use seatbelts and child restraints.
- Bring chains if you are traveling to mountain areas - it is recommended to have chains in your vehicle during winter months. Make sure your gas tank is full before going up the hill. Go to www.dot.ca.gov/hq/traffops/trucks/ops-guide/chains.html for more chain information.
- Chain installers are available on most mountain routes during chain control - please use the Caltrans approved installers with authorized bibs - for your safety and to protect your vehicle. Unauthorized vendors are subject to prosecution.
- For long trips - bring water, warm clothing/blankets, medications, snacks and other necessary items.
- Listen to local radio stations or check traffic reports on television for traffic conditions on the routes you plan to travel.
- Don't go around road closure signs in the event of inclement weather conditions. Never drive through running water or flooded roadways.
- Be a safe and courteous driver. It only adds a few minutes to your travel time and makes it a better drive for everyone.
This week and next are not looking good for those who travel Interstate 15 in the Ontario/Rancho Cucamonga area late night/early morning.
As part of the ongoing construction on Interstate 15, Caltrans and the contractor will be closing the freeway for several nights in order to install freeway signs.
From 10 p.m. to 6 a.m. November 17 through 22, the northbound 15 will be closed at Jurupa Avenue.
From 10 p.m. to 6 a.m. November 21 through 23, the southbound 15 will be closed at Foothill Boulevard.
Caltrans is urging commuters to use alternate routes. Signs will be posted in advance.
For the latest information on the I-15 construction project, follow i15ontfix on Twitter.
Follow the jump for a map of the affected area.
As part of the ongoing construction on Interstate 15, Caltrans and the contractor will be closing the freeway for several nights in order to install freeway signs.
From 10 p.m. to 6 a.m. November 17 through 22, the northbound 15 will be closed at Jurupa Avenue.
From 10 p.m. to 6 a.m. November 21 through 23, the southbound 15 will be closed at Foothill Boulevard.
Caltrans is urging commuters to use alternate routes. Signs will be posted in advance.
For the latest information on the I-15 construction project, follow i15ontfix on Twitter.
Follow the jump for a map of the affected area.
Continue reading Interstate 15 closures, November 17 through 23.
Caltrans crews will continue repairing the Barton Road bridge in Grand Terrace, requiring the closure of one lane and an off-ramp on the northbound 215 Freeway. The closure is scheduled to last until 2 p.m.
The California Highway Patrol issued a Sig Alert this morning due to Caltrans road work on the 215 Freeway in Grand Terrace. One lane was closed at 9:44 a.m. so Caltrans could fix the Barton Road bridge. The duration of the closure was not known.
Damaged concrete forced the closure of the interchange from the southbound 215 Freeway to the eastbound 60 Freeway. Roadwork also blocked lanes on the eastbound 60 at Chicago Avenue, the California Highway Patrol said. The 6 a.m. closure was scheduled to last until 3 p.m.
The CHP issued a traffic advisory due to the Highway 395 off-ramp from the northbound 15 Freeway being closed for construction.
Caltrans closed eastbound lanes on Highway 18 between Pine Knot Boulevard and Georgia Street for road work. The closure was scheduled to last until about 3 p.m.
Due to the ongoing construction on Interstate 15, the connectors from east- and westbound Interstate 10 to northbound Interstate 15, and the Fourth Street off-ramp from northbound Interstate 15, are scheduled to be closed from 10 p.m. today (August 6) through 5 a.m. Monday (August 9).
Detour signs will be posted to indicate alternate routes.
For the latest information on the I-15 construction project, follow i15ontfix on Twitter.
Follow the jump for a map of the affected area.
Detour signs will be posted to indicate alternate routes.
For the latest information on the I-15 construction project, follow i15ontfix on Twitter.
Follow the jump for a map of the affected area.
The CHP issued a traffic advisory on the northbound 15 Freeway north of Wild Wash Road after the fast lane was closed for road repair. The closure, about a mile long, is north of Apple Valley.
Due to the ongoing construction on Interstate 15, the northbound connectors to both east- and westbound Interstate 10 are scheduled to be closed from 10 p.m. today (July 30) through 5 a.m. Monday (August 2).
Detour signs will be posted to indicate alternate routes.
For the latest information on the I-15 construction project, follow i15ontfix on Twitter.
Follow the jump for a map of the affected area.
Detour signs will be posted to indicate alternate routes.
For the latest information on the I-15 construction project, follow i15ontfix on Twitter.
Follow the jump for a map of the affected area.
Due to the ongoing construction on Interstate 15, the northbound connectors to both east- and westbound Interstate 10 are scheduled to be closed from 10 p.m. today (July 9) through 5 a.m. Monday (July 12).
Detour signs will be posted to indicate alternate routes.
For the latest information on the I-15 construction project, follow i15ontfix on Twitter.
Follow the jump for a map of the affected area.
Detour signs will be posted to indicate alternate routes.
For the latest information on the I-15 construction project, follow i15ontfix on Twitter.
Follow the jump for a map of the affected area.
One lane of northbound Highway 330 and the Highland Avenue exit were closed about 9 a.m. for road work. The closure was scheduled to last until 4 p.m.
Caltrans crews plan to close the southbound 15 Freeway connector to the east- and westbound 60 Freeway from Friday night until Monday morning for roadwork.
The slow lane on the southbound 15 will also be closed from Philadelphia Street to the 60 Freeway interchange in Ontario for the Ont Fix project.
The closures are scheduled to run from 10 p.m. Friday until 5 a.m. Monday, Caltrans officials said.
The $52 million Ont Fix project includes bridge widening, median paving and pavement replacement, among other improvements.
View I-15 construction, June 11 to 14 in a larger map
The slow lane on the southbound 15 will also be closed from Philadelphia Street to the 60 Freeway interchange in Ontario for the Ont Fix project.
The closures are scheduled to run from 10 p.m. Friday until 5 a.m. Monday, Caltrans officials said.
The $52 million Ont Fix project includes bridge widening, median paving and pavement replacement, among other improvements.
View I-15 construction, June 11 to 14 in a larger map
A Caltrans closure on the Etiwanda Avenue off-ramp from the eastbound 10 Freeway backed up traffic, prompting the CHP to issue a Sig Alert. The off-ramp was scheduled to be closed until Thursday for repairs.
Due to the ongoing construction on Interstate 15, the northbound Jurupa Street on- and off-ramps from I-15 are scheduled to be closed from 10 p.m. Friday (May 21) through 5 a.m. Monday (May 24).
Detour signs will be posted to indicate alternate routes.
For the latest information on the I-15 construction project, follow i15ontfix on Twitter.
Follow the jump for a map of the affected area.
Detour signs will be posted to indicate alternate routes.
For the latest information on the I-15 construction project, follow i15ontfix on Twitter.
Follow the jump for a map of the affected area.
Continue reading Northbound I-15 Jurupa Street on- and off-ramps closed this weekend.
Due to the ongoing construction on Interstate 15, the north- and southbound I-15 connectors from eastbound SR-60 are scheduled to be
closed from 10 p.m. Friday (May 14) through 5 a.m. Monday (May 17).
Detour signs will be posted to indicate alternate routes.
For the latest information on the I-15 construction project, follow i15ontfix on Twitter.
Follow the jump for a map of the affected area.
Detour signs will be posted to indicate alternate routes.
For the latest information on the I-15 construction project, follow i15ontfix on Twitter.
Follow the jump for a map of the affected area.
Continue reading Connectors from eastbound SR-60 to I-15 closed this weekend.
Highway 330 reopened about 8 p.m. Monday night, but Caltrans officials say there could be minor delays on the highway while workers make the finishing touches on the road.
For the next three to four weeks, construction crews will be doing intermittent traffic control between 7 a.m. and 6 p.m. There will be no roadwork May 21-23 during the AMGEN Tour of California bike race.
A 12-mile stretch of the highway was closed March 16 after a pipe running about 80 feet below the highway collapsed.
The I-215 widening project continues with a particularly burdensome closure for downtown commuters: 2nd Street will be closed between G and I streets for eight weeks beginning at 7 a.m. Monday (April 26). That's through June 18, by my calculation.
That's on top of the two-year closure of the southbound 27th Street on-ramp and and northbound 27th Street off-ramp and the six-week closure (five weeks remaining) of the connector from the southbound I-215 to the eastbound SR-210.
Add to that various on- and off-ramp and lane closures from 8 p.m. to 6 a.m. Sunday (April 25) through Thursday (April 29) and you've got a definite reason to avoid I-215 at night.
For further information on the project, click here. For a PDF file with a list of closures for the upcoming week, click here.
For up-to-date information on the project, follow 215NEWS on Twitter.
View I-215 construction, April 25 - 29 in a larger map
That's on top of the two-year closure of the southbound 27th Street on-ramp and and northbound 27th Street off-ramp and the six-week closure (five weeks remaining) of the connector from the southbound I-215 to the eastbound SR-210.
Add to that various on- and off-ramp and lane closures from 8 p.m. to 6 a.m. Sunday (April 25) through Thursday (April 29) and you've got a definite reason to avoid I-215 at night.
For further information on the project, click here. For a PDF file with a list of closures for the upcoming week, click here.
For up-to-date information on the project, follow 215NEWS on Twitter.
View I-215 construction, April 25 - 29 in a larger map
Due to the ongoing construction on Interstate 15, the east- and westbound SR-60 connectors from southbound I-15 are scheduled to be closed from 10 p.m. Friday (April 23) through 5 a.m. Monday (April 26).
Detour signs will be posted to indicate alternate routes.
For the latest information on the I-15 construction project, follow i15ontfix on Twitter.
View I-15 construction, April 23 to 26 in a larger map
Detour signs will be posted to indicate alternate routes.
For the latest information on the I-15 construction project, follow i15ontfix on Twitter.
View I-15 construction, April 23 to 26 in a larger map
The fast lane was closed on the northbound 15 Freeway at Highway 247 to the 40 Freeway for road work.
Two lanes were closed on the northbound 15 Freeway at Highway 58 for road construction. The closure was scheduled to last until 2 p.m.
Due to the continuing I-215 widening project, the northbound 27th Street off-ramp and the southbound 27th Street on-ramp will be closed for approximately two years beginning Friday (April 2).
Suggested detours are as follows:
For the latest updates on the I-215 widening project, follow 215NEWS on Twitter.
View 27th Street on- and off-ramp closures in a larger map
Suggested detours are as follows:
- Northbound: Exit Muscupiabe Drive, turn right and continue north to 27th Street.
- Southbound: Travel south on Mount Vernon Avenue, turn left onto Highland Avenue, and enter southbound on SR-259.
For the latest updates on the I-215 widening project, follow 215NEWS on Twitter.
View 27th Street on- and off-ramp closures in a larger map
One lane was closed on the westbound 10 near Oak Valley Parkway for road work. The closure was schedule to last until 2 p.m.
Due to overhead electrical wire maintenance, Southern California Edison construction crews will briefly be closing both north- and southbound lanes of I-15 in Oak Hills.
The closures are scheduled to take place from 6 to 10 a.m. Saturday (March 27) and Sunday (March 28).
Southbound lanes will be closed at Joshua Street. Northbound lanes will be closed at Oak Hills Road.
During this time, traffic will be diverted to frontage roads.
Detour signs will be posted in advance.
CHP will be monitoring the flow of traffic, but allow for additional time if traveling through the area during the closure.
View I-15 freeway closure, March 27 & 28 in a larger map
The closures are scheduled to take place from 6 to 10 a.m. Saturday (March 27) and Sunday (March 28).
Southbound lanes will be closed at Joshua Street. Northbound lanes will be closed at Oak Hills Road.
During this time, traffic will be diverted to frontage roads.
Detour signs will be posted in advance.
CHP will be monitoring the flow of traffic, but allow for additional time if traveling through the area during the closure.
View I-15 freeway closure, March 27 & 28 in a larger map
Due to the ongoing construction on Interstate 15, the westbound I-10 connector to southbound I-15 and the southbound I-15 Jurupa Street off-ramp, are scheduled to be closed from 10 p.m. Friday (March 19) through 5 a.m. Monday (March 22).
Detour signs will be posted to indicate alternate routes.
For the latest information on the I-15 construction project, follow i15ontfix on Twitter.
View I-15 construction, March 19-22 in a larger map
Detour signs will be posted to indicate alternate routes.
For the latest information on the I-15 construction project, follow i15ontfix on Twitter.
View I-15 construction, March 19-22 in a larger map
Due to a culvert failure, SR-330 will be closed for three to four weeks, depending on the availability of materials to do the repairs, beginning today (March 16).
The highway will be closed from Highland Avenue in San Bernardino to Live Oak Drive in Running Springs.
SR-330 will be closed to downbound traffic beginning early afternoon today. It will be closed to upbound traffic beginning at 7 p.m. this evening.
Use SR-18 and SR-38 as alternates during the closure.
View SR-330 closure in a larger map
The highway will be closed from Highland Avenue in San Bernardino to Live Oak Drive in Running Springs.
SR-330 will be closed to downbound traffic beginning early afternoon today. It will be closed to upbound traffic beginning at 7 p.m. this evening.
Use SR-18 and SR-38 as alternates during the closure.
View SR-330 closure in a larger map
Caltrans crews closed two lanes of Highway 330 at Highland Avenue this morning to repair erosion damage. The closure on the border of Highland and San Bernardino was scheduled to last until 4 p.m., according to the California Highway Patrol.
The CHP issued a Sig Alert at 10:50 a.m. due to Caltrans roadwork, which blocked the slow lane on the westbound 60 west of Ramona Avenue. The Sig Alert was expected to last four hours.
Due to the ongoing construction on Interstate 15, both the east- and westbound I-10 connectors to southbound I-15, along with the southbound I-15 Jurupa Avenue off-ramp, are scheduled to be closed from 10 p.m. Friday (March 12) through 5 a.m. Monday (March 15).
Detour signs will be posted to indicate alternate routes.
For the latest information on the I-15 construction project, follow i15ontfix on Twitter.
Update: The closure will not include the southbound Jurupa Avenue off-ramp.
View I-15 construction, March 12-15 in a larger map
Detour signs will be posted to indicate alternate routes.
For the latest information on the I-15 construction project, follow i15ontfix on Twitter.
Update: The closure will not include the southbound Jurupa Avenue off-ramp.
View I-15 construction, March 12-15 in a larger map
Construction continues on the Interstate 215 widening project in San Bernardino, with the southbound lanes between Mount Vernon Avenue/27th Street to the SR-259 interchange scheduled to be closed from midnight to 5 a.m. Thursday (March 11) and Friday (March 12) morning.
Also scheduled to be closed at times are various on- and off-ramps near downtown from 8 p.m. tonight to 6 a.m. Thursday (March 11):
For the latest information, follow 215NEWS on Twitter.
View I-215 construction, March 10-12 in a larger map
Also scheduled to be closed at times are various on- and off-ramps near downtown from 8 p.m. tonight to 6 a.m. Thursday (March 11):
- Southbound Sixth Street off-ramp
- Southbound Third Street off-ramp
- Southbound Second Street on-ramp
- Northbound Second street on- and off-ramps
- Northbound Sixth Street off-ramp
For the latest information, follow 215NEWS on Twitter.
View I-215 construction, March 10-12 in a larger map
Tomorrow's scheduled early morning southbound Interstate 215 closure at Highland Avenue has been changed to a northbound closure.
The northbound closure is expected from midnight to 5 a.m. tomorrow (March 3).
Caltrans is suggesting the following detour:
For more information, follow Caltrans District 8's 215 News on Twitter at http://www.twitter.com/215NEWS.
View I-215 construction, February 22-23 in a larger map
The northbound closure is expected from midnight to 5 a.m. tomorrow (March 3).
Caltrans is suggesting the following detour:
- Exit Muscupiabe Drive, travel north, turn left on 27th Street, and re-enter I-215.
For more information, follow Caltrans District 8's 215 News on Twitter at http://www.twitter.com/215NEWS.
View I-215 construction, February 22-23 in a larger map
The CHP issued a traffic advisory on the southbound 215 Freeway at Washington Street because workers were repairing a bridge. The slow lane and off-ramp were closed. The traffic advisory was cancelled at 9:58 a.m.
Southbound Interstate 215 will be closed at Highland Avenue from midnight to 5 a.m. Wednesday (February 24) and Thursday (February 25).
Caltrans is suggesting the following detour:
For more information, follow Caltrans District 8's 215 News on Twitter at http://www.twitter.com/215NEWS.
View I-215 construction, February 24 & 25 in a larger map
Caltrans is suggesting the following detour:
- Exit 27th Street, turn right, travel south, turn left at Highland Avenue and re-enter the freeway at SR-259.
For more information, follow Caltrans District 8's 215 News on Twitter at http://www.twitter.com/215NEWS.
View I-215 construction, February 24 & 25 in a larger map
Northbound Interstate 215 is scheduled to be closed at Highland Avenue from midnight to 5 a.m. Monday (February 22) and Tuesday (February 23).
Caltrans is suggesting the following detour:
Southbound Interstate 215 will be closed from midnight to 5 a.m. Wednesday (February 24) and Thursday (February 25).
For more information, follow Caltrans District 8's 215 News on Twitter at http://www.twitter.com/215NEWS.
View I-215 construction, February 22-23 in a larger map
Caltrans is suggesting the following detour:
- Exit Muscupiabe Drive, travel north, turn left on 27th Street, and re-enter I-215.
Southbound Interstate 215 will be closed from midnight to 5 a.m. Wednesday (February 24) and Thursday (February 25).
For more information, follow Caltrans District 8's 215 News on Twitter at http://www.twitter.com/215NEWS.
View I-215 construction, February 22-23 in a larger map
The northbound Second Street and Base Line off-ramps from Interstate 215 will be closed from 8 p.m. to 6 a.m. Tuesday (February 16) through Thursday (February 18).
Caltrans is suggesting the following detours:
They're not offering a detour, since at least one lane will be open, but you might want to consider an alternate route.
Fair warning: Full freeway closures early morning Tuesday through Thursday next week.
For more information, follow Caltrans District 8's 215 News on Twitter at http://www.twitter.com/215NEWS.
View I-215 construction, February 16-18 in a larger map
Caltrans is suggesting the following detours:
- Second Street: Exit Mill Street, turn right, and turn left on G Street.
- Base Line: Exit Fifth Street, turn left on H Street, and travel north.
They're not offering a detour, since at least one lane will be open, but you might want to consider an alternate route.
Fair warning: Full freeway closures early morning Tuesday through Thursday next week.
For more information, follow Caltrans District 8's 215 News on Twitter at http://www.twitter.com/215NEWS.
View I-215 construction, February 16-18 in a larger map